Posted on: July 3, 2019[ARCHIVED] Weekly Traffic Impact Report

PROJECT: | CORP YARD BUILDING |
STATUS: | Work is in progress. |
IMPACT: | Signs will be in place for minor construction:
- Heavy truck traffic entering and exiting the site
hauling asphalt on Plainview Road and Litt Road
- Use caution and avoid the area if possible.
Motorists are advised to drive slowly and use alternate routes when possible. |
PROJECT: | BUS TURNOUT ON MAZE BOULEVARD/STATE ROUTE 132 |
STATUS: | Work is in progress. Project is expected to be completed by August 2019. |
IMPACT: | Signs will be in place for minor construction:
- EMERALD AVENUE TO SPENCER AVENUE Work on EB shoulder
Motorists are advised to drive slowly and use alternate routes when possible. |
PROJECT: | GROUNDWATER MONITORING WELLS |
STATUS: | Work is in progress. Project is expected to be completed by August 2019. |
IMPACT: | Construction signs will be set up with minor traffic control at:
- DE LA PENA DRIVE BETWEEN CAMINO REAL AND VANDER DRIVE
Motorists are advised to drive slowly and use alternate routes when possible. |