[ARCHIVED] Traffic Impact Report

PROJECT: STATE ROUTE 99/PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT

STATUS: Work is in progress. Project completion is expected by 2017.
For the most recent traffic control updates, View This Document

IMPACT:

8/22/16 to 8/26/16 7:00 a.m. – 3:30 p.m.
NB Salida Boulevard starting 400ft south of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 800ft north – Closure of the single NB lane. Traffic control/flaggers will be in place to allow traffic to pass through using the single SB lane.

*Note: Work on Salida Boulevard is anticipated for 1 day only, exact dates of when work will happen depends on crew availability.

8/22/16 to 8/26/16 7:00 a.m. – 3:30 p.m.
NB Salida Boulevard starting 700ft north of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 600ft north – Closure of the single NB lane. Traffic control/flaggers will be in place to allow traffic to pass through using the single SB lane.

*Note: Closure depends on how much room contractor has to pour sidewalk, so lane may be open during this time frame.

8/22/16 to 8/26/16 7:00 a.m. – 3:30 p.m.
EB Pelandale Avenue starting 300ft west of the intersection of Sisk Road/Pelandale Avenue and going approximately to the intersection of Sisk Road/Pelandale Avenue – Closure of the number 3 lane.

8/22/16 to 8/26/16 7:00 a.m. – 3:30 p.m.
SB Sisk Rd. starting 300ft north of the intersection of Sisk Road/Pelandale Avenue and going approximately 100ft south of the intersection of Sisk Road/Pelandale Avenue – Closure of the number 4 lane.

8/22/16 to 8/25/16 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.

8/22/16 to 8/25/16 7:00 a.m. – 3:30 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.

8/26/16 7:00 a.m. – 2:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.

8/26/16 7:00 a.m. – 2:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.

8/21/16-8/22/16 10:00 p.m. – 5:00 a.m.
SR 99 Northbound starting 3,000lf south of the new Pelandale Overcross to 2,200lf north of the new Pelandale Overcross – Closure of the number 3 lane only.

8/22/16-8/23/16 8:00 p.m. – 5:00 a.m.
SR 99 Northbound starting 3,000lf south of the new Pelandale Overcross to 2,200lf north of the new Pelandale Overcross – Closure of the number 3 & 2 lanes.

8/22/16-8/23/16 10:00 p.m. – 4:00 a.m.
SR 99 Northbound On-Ramp & Off-Ramp – Full ramp closure.

8/22/16-8/23/16 10:00 p.m. – 4:00 a.m.
SR 99 Southbound On-Ramp & Off-Ramp – Full ramp closure.

8/23/16-8/24/16 8:00 p.m. – 5:00 a.m.
SR 99 Northbound starting 3,000lf south of the new Pelandale Overcross to 2,200lf north of the new Pelandale Overcross – Closure of the number 1 & 2 lanes.

8/23/16-8/24/16 8:00 p.m. – 6:00 a.m.
SR 99 Southbound starting 2,200lf north of the new Pelandale Overcross to 3,000lf south of the new Pelandale Overcross – Closure of the number 1 & 2 lanes.

8/24/16-8/25/16 8:00 p.m. – 6:00 a.m.
SR 99 Southbound starting 2,200lf north of the new Pelandale Overcross to 3,000lf south of the new Pelandale Overcross – Closure of the number 2 & 3 lanes.

8/24/16-8/25/16 10:00 p.m. – 4:00 a.m.
SR 99 Northbound On-Ramp & Off-Ramp – Full ramp closure.

8/24/16-8/25/16 10:00 p.m. – 4:00 a.m.
SR 99 Southbound On-Ramp & Off-Ramp – Full ramp closure.

PROJECT: STRENGTHEN & REPLACE WATER SYSTEM S. 9TH STREET INDUSTRIAL AREA
STATUS: Work is in progress. Project is expected to be completed by September 30th, 2016.
IMPACT: Construction is ongoing on South 9th Street, Sonora Ave, Hosmer Avenue, Lombardo Avenue, Bystrum Road and Latimer Avenue.

Detours and lane shifts will be in place. Traffic will be impacted due to lane closures and flagging. Motorists are advised to drive slowly and use alternate routes when possible.