7/11/16 to 7/15/16 7:00 a.m. – 3:30 p.m.
NB Salida Boulevard starting 400ft south of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 800ft north – Closure of the single NB lane. Traffic control/flaggers will be in place to allow traffic to pass through using the single SB lane.
*NOTE: Work on Salida is anticipated for 1 day only, exact dates of when work will happen depends on crew availability.
7/11/16 to 7/13/16 9:00 a.m. – 11:30 a.m. / 1:30 p.m. – 3:30 p.m.
EB & WB Pelandale Avenue starting 200ft west of the intersection of Sisk Road/Pelandale Avenue and going approximately 350ft east of the intersection of Sisk Road/Pelandale Avenue
Closure of the No. 2 lane; only one direction at a time will be closed.
7/11/16 to 7/13/16 9:00 a.m. – 11:30 a.m. / 1:30p.m. – 3:30 p.m.
NB Sisk Road starting 200ft north of the intersection of Sisk Road/Pelandale Avenue
and going approximately 200ft south of the intersection of Sisk Road/Pelandale Avenue
Closure of the No. 2 lane only.
7/11/16 to 7/13/16 9:00 a.m. – 11:30 a.m. / 1:30 p.m. – 3:30 p.m.
SB Sisk Road starting 200ft south of the intersection of Sisk Road/Pelandale Avenue
and going approximately 200ft north of the intersection of Sisk Road/Pelandale Avenue
Closure of the No. 2 left turn lane only.
7/13/16 to 7/14/16 9:00 p.m. – 5:00 a.m.
EB & WB Pelandale Avenue starting 200ft west of the intersection of Sisk Road/Pelandale Avenue and going approximately 350ft east of the intersection of Sisk Road/Pelandale Avenue
Closure of the No. 2 lane; only one direction at a time will be closed.
7/13/16 to 7/14/16 9:00 p.m. – 5:00 a.m.
NB Sisk Road starting 200ft north of the intersection of Sisk Road/Pelandale Avenue
and going approximately 200ft south of the intersection of Sisk Road/Pelandale Avenue
Closure of the No. 2 lane only.
7/13/16 to 7/14/16 9:00 p.m. – 5:00 a.m.
SB Sisk Road starting 200ft south of the intersection of Sisk Road/Pelandale Avenue and going approximately 200ft north of the intersection of Sisk Road/Pelandale Avenue
Closure of the No. 2 left turn lane only.
PROJECT: 2014 - 2015 STORM DRAIN IMPROVEMENTS
STATUS: Work is in progress. Project is expected to be completed by end of July 2016.
IMPACT: Orangeburg Avenue & Martin Avenue
Expect periodic lane closures using cones, construction signs and road closures.
Motorists are advised to drive slowly through the construction zones and use alternate routes when possible.
PROJECT: SLURRY SEAL - TULLY ROAD FROM BOWEN AVENUE TO WOODROW AVENUE
STATUS: Work will begin on Monday, July 11th, 2016. Project is expected to be completed by July 22nd, 2016.
IMPACT: Traffic will be impacted due to lane closures and fresh oil. Lanes will be reduced to one lane of traffic each direction. Motorists will need to use detours that will be in place or alternate routes. Please drive slow through the cone zone.