[ARCHIVED] Weekly Traffic Impact Report Available Online

PROJECT:

La Loma Phase 2B strengthen & Replace water mains 

STATUS:

Work is in progress. Project is expected to be completed by November 2018.

IMPACT:

Construction signs will be set up to provide traffic control on:

Closure of alleys between Miller Avenue to Yosemite Boulevard,

from Phoenix Avenue to El Vista Avenue

Closure of Phoenix Avenue, from Roble Avenue to Encina Avenue

Motorists are advised to drive slowly and use alternate routes when possible.


PROJECT:

DRYWELL INSTALL

STATUS:

Work is in progress. Project is expected to be completed by the end of March 2018.

IMPACT:

  • Construction signs will be set up with minor traffic control at Dartmouth Court.
  • There will be construction equipment moving in this area.
  • Motorists are advised to drive slowly and use alternate routes if possible.


PROJECT:

Horizontal Drain

STATUS:

Work is in progress. Project is expected to be completed by the end of March 2018.

IMPACT:

  • Construction signs will be set up with minor traffic control at the intersection of Kensington Drive and Wellington Drive. There will be construction equipment moving in this area. Motorists are advised to drive slowly and use alternate routes if possible.


PROJECT:

La Loma Phase 2B

STATUS:

Work in Progress

IMPACT:

Construction Signs will be in place to allow for closure of the No. 2 lane on Southbound El Vista Avenue from Miller Avenue to Yosemite Boulevard.

Additional Info...