Traffic Impact Report
April 27th, 2017
-----------------------------------------------------------------------------------------------------------------------------
project:
| HAHN & RUMBLE LIFT STATION REPLACEMENTS
|
STATUS:
| Work is in progress. Project is expected to be completed by March 2018.
|
IMPACT:
| Construction signs will be set up with minor traffic control at 2 locations: ?*Sylvan Park on Rumble Road between Coffee Road and Keller Street ?*Honey Creek Road and Nightingale Drive
Motorists are advised to drive slowly and use alternate routes when possible.
|
-----------------------------------------------------------------------------------------------------------------------------
project:
| CODONI TRANSMISSION MAINS
|
STATUS:
| Work is in progress. Project is expected to be completed by June 2017.
|
IMPACT:
| Lane shift on Westbound & Eastbound State Route 132 Yosemite Boulevard between Codoni Avenue to Claus Road. Left turn lane from Eastbound Yosemite Boulevard on to Southbound Codoni Avenue will be closed. Construction signs are set up with traffic control and K-Rail. There will be construction equipment moving in this area. Motorists are advised to drive slowly and use alternate routes if possible.
|
-----------------------------------------------------------------------------------------------------------------------------
project:
| MARK RANDY/TORRID DIABLO LIFT STATION IMPROVEMENTS
|
STATUS:
| Work is in progress. Project is expected to be completed by June 2018.
|
IMPACT:
| Construction signs will be set up with minor traffic control at two locations, the intersection of Mark Randy Place and McHenry Avenue, and the intersection of Diablo Avenue and Torrid Avenue. There will be construction equipment moving in this area. Motorists are advised to drive slowly and use alternate routes if possible.
|
-----------------------------------------------------------------------------------------------------------------------------
project:
| ROSELLE AVENUE WIDENING PROJECT
|
STATUS:
| Work is in progress. Project is expected to be completed by November 2017.
|
IMPACT:
| Northbound Roselle Avenue between Floyd Avenue and Sylvan Avenue – Closure of both lanes, traffic will be shifted into the number 1 southbound lane. *At least one lane of traffic will be open at all times.
Southbound Roselle Avenue between Floyd Avenue and Sylvan Avenue – Closure of the number 1 lane *At least one lane of traffic will be open at all times.
Eastbound & Westbound Kodiak Drive will be closed in both directions at Roselle Avenue. Closure will remain in place until November 2017. Traffic is to utilize the detour signs in place to find alternate routes.
|