PROJECT: STATE ROUTE 99/PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT
STATUS: Work is in progress. Project completion is expected by the end of February 2017.
For the most recent traffic control updates, go to: www.SR99Pelandale.org
IMPACT:
03/06/17 to 03/09/17 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
03/06/17 to 03/09/17 7:00 a.m. – 3:30 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.
03/06/17 to 03/09/17 7:00 a.m. – 3:30 p.m.
SR 99 Southbound & Northbound – Closure of the shoulders only.
03/10/17 7:00 a.m. – 3:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
03/10/17 7:00 a.m. – 3:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.