Road Closures & Traffic

Posted on: March 31, 2022

[ARCHIVED] Weekly Traffic Impact Report Week of March 31, 2022

Crows Landing Road Pavement Rehabilitation

Project Status

Work is in progress. Project is expected to be completed by the end of May 2022.

Traffic Impacts

Traffic control will be in place:

  • Southbound Crows Landing Road is open from SR 99 off-ramp to Hatch Road. 
  • Southbound Crows Landing Road is closed at northside of SR 99 Bridge and detoured onto northbound SR 99 at on-ramp.
  • Northbound traffic will be detoured to northbound and southbound on-ramps SR99. 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Sewer Replacement Project 

Project Status

Work is in progress. Project is expected to be completed by the end of April 2022.

Traffic Impacts

Construction signs, detours and possible road closure for one week.

  • Sutter Avenue and Pelton Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

State Route 132 West Freeway Expressway Phase 1 Project

Project Status

For more information please visit the State Route 132 Project website.

Traffic Impacts

  • The Southbound 99 off ramp at Maze 132 (L Street) is currently under a long term full closure. Southbound motorists will be asked to exit at the following "Central Modesto" exit.
  • Full closure to all traffic on Rosemore Avenue between Kansas Avenue to the north and Elm Avenue to the south. Expected to be completed by May 31st, 2022. This will allow for the completion of the new Rosemore Overcrossing of the new SR-132 freeway alignment. Detour routes will be Carpenter Road to the east and North Dakota Avenue to the west.
  • The  SR 99 NB on-ramp at L Street is fully closed until May 31st, 2022 for the construction of a new NB SR 99 general purpose auxiliary lane and on-ramp. Motorists wishing to enter NB 99 at this location will be detoured to the NB 99 on-ramp at I Street. 
  • Starting this Friday night, April 1st at 7:00 p.m., Emerald Avenue between Kansas Avenue and Elm Street will be fully closed to traffic until Monday morning April 4th at 5:00 a.m.  Traffic will be detoured west to Carpenter Road. This closure is necessary in order to replace the roadway section beneath the new SR-132 overcrossing.    

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Asphalt Patching – City Crews

Project Status

On Monday, April 4th & Tuesday April 5th, 2022.

Traffic Impacts

Lane closures will be in place:

  • On B Street between 9th Street and 10th Street and 10th Street to Morton Boulevard. 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Concrete – City Crews (updated)

Project Status

On Tuesday April 5th through Friday April 8th, 2022  7:00 a.m. – 4:00 p.m.

Traffic Impacts

Southbound lane closures will be in place:

  • On Sunrise Avenue between Norwegian Avenue and East Briggsmore Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Sutter Sanitary Sewer Trunk Rehabilitation Project, Phase 1

Project Status

Work is in progress.  Project is expected to be completed by the end of April 2022.

Traffic Impacts

Construction signs will be in place:

  • Linden Street will be closed to through traffic.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Paradise Road Pavement Rehabilitation

Project Status

Work is in progress. Project is expected to be completed by July 2022.  

Traffic Impacts

Traffic control will be in place:

  • Paradise Road from Carpenter Road to Chicago Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Upgrade to ATMS 2019

Project Status 

Work is in progress. Project is expected to be completed by May 2022.

Traffic Impacts

Traffic control will be in place:

  • Standiford Avenue from Sisk Road to Oakdale Road
  • Briggsmore Avenue from Sisk Road to Oakdale Road

Motorists are advised to drive slowly with caution and use alternate routes when possible.

PG&E Project

Project Status

Work is in progress. Project is expected to be completed by April 2022.

Traffic Impacts

Construction area signs will be in place.

  • Lane shifts and lane closures will be in place mostly on east and west bound Clevenger Drive from Carver Road to Tully Road. 
  • Some lane closures will be in place on Carver Road and Tully Road north and south bound sides. 

Motorists are advised to drive slowly with caution and use alternate routes when possible.