[ARCHIVED] Weekly Traffic Impact Report Week of December 29, 2021

State Route 132 West Freeway Expressway Phase 1 Project

Project Status

For more information please visit the State Route 132 Project website.

Traffic Impacts

  • The Southbound 99 off ramp at Maze 132 (L Street) is currently under a long term full closure. Southbound motorists will be asked to exit at the following "Central Modesto" exit. 

Sutter Sanitary Sewer Trunk Rehabilitation Project, Phase 1

Project Status

Work is in progress.  Project is expected to be completed by April 2022.

Traffic Impacts

Construction signs will be in place:

  • Linden Street will be closed to thru traffic.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Bangs Avenue Paving 

Project Status

Work is in progress and expected to be competed by January 14th, 2022.  

Traffic Impacts

Construction signs will be in place:

  • Eastbound lane of Bangs Avenue is closed between Carver Road and Tully Road.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

PG&E Project

Project Status

Work is in progress.

Traffic Impacts

Construction area signs will be in place.

  • Lane shifts and lane closures will be in place mostly on east and west bound Woodland Avenue and Coldwell Avenue from Graphics Drive to Tully Road. 
  • Some lane closures will be in place on 9th Street north and south bound sides.  

Motorists are advised to drive slowly with caution and use alternate routes when possible.

PG&E Project

Project Status

Work is in progress.

Traffic Impacts

Construction area signs will be in place.

  • Lane shifts and lane closures will be in place mostly on east and west bound Clevenger Drive from Carver Road to Tully Road. 
  • Some lane closures will be in place on Carver Road and Tully Road north and south bound sides. 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Crows Landing Road Pavement Rehabilitation

Project Status 

Work is in progress. Project is expected to be completed by March 2022.

Traffic Impacts

Traffic control will be in place:

  • Crows Landing Road from Pecos Avenue to Hatch Road

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Scenic Pavement Rehabilitation

Project Status 

Work is in progress. 

Traffic Impacts

Traffic control signs and possible roundabout closure with flagger:

    at La Loma Avenue and Buena Vista

Motorists are advised to drive slowly with caution and use alternate routes when possible.