Posted on: December 10, 2020

[ARCHIVED] Weekly Traffic Impact Report

Traffic Control Measures in relatively close proximity to a construction site.

Project:
State Route 132 West Freeway Expressway Phase 1 Project
Status:
Work is in progress.
Impact:
Please visit the project website for more information
Project:
New Jennings WQC Plant Entrance/Exit
Status:
Work is in progress. Project is expected to be completed by the end of May 2021.
Impact:
Construction signs will be in place for road closures 24/7. Roads will be closed to through traffic.
  • Road closure on Jennings Road between Monte Vista Avenue & Taylor Road through December 31, 2020
Motorists are advised to drive slowly with caution and use alternate routes when possible.

Project:
North Trunk Sewer
Status:
Work is in progress. Project is expected to be completed by the end of December 2020.
Impact:
Construction signs will be in place for floating lane closures during working hours and road closures on:
  • Road closure on Bangs Avenue between Carver Avenue and Tully Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.

Project:
McHenry Avenue & Stewart Road
Status:
Work is in progress. Project is expected to be completed by the end of December 2020.
Impact:
Minor traffic control to lane closures periodically on McHenry shifting traffic by construction.
Periodic full road closure on Stewart Road at McHenry diverting traffic to an alternate route.
  • McHenry Avenue and Stewart Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.

Project:
PG&E
Status:
Work is in progress.
Impact:
Construction signs will be in place for lane shift during working hours on:
  • Coffee Road/Claratina Avenue lane shift west of roundabout
  • Bangs Avenue - closed daily between Dale Road & Prescott Road
  • Dale Road south bound lane shifts with No. 02 lane & shoulder closures daily
Motorists are advised to drive slowly with caution and use alternate routes when possible.

Project:
Yosemite Boulevard Valve Box Replacement
Status:
Work is in progress. Project is expected to be completed by the end of January 2021.
Impact:
Construction signs will be in place. Heavy equipment moving in and out of the area.
  • Yosemite Boulevard between Las Flores Avenue and Phoenix Avenue
Motorists are advised to drive slowly with caution and use alternate routes when possible.

Project:
Sonoma Sanitary Sewer Trunk Extension
Status:
Work is scheduled to begin on Monday 12/14/2020. Project is expected to be completed by June 2021.
Impact:
Minor Traffic Control
  • Lane shift from 2 lanes to 1 on Sylvan Avenue from Wood Sorrel Drive to Aria Way - both directions
  • Jeffrey Drive
  • Carl Way
Motorists are advised to drive slowly with caution and use alternate routes when possible.