Purpose
The proposed improvements replaced approximately 3,500 foot of sewer pipe from the Shackelford Crossing heading north along Zeff Road, rehabilitated the existing pipe, installed a secondary line beneath South Route 99 for about 800 foot, and installed a Parshall Flume at Hosmer.
Financial
Budget: $5,700,000.00
Estimated Time of Completion
This project is now complete.
Project Manager
Pete Kambel
Council District
District 2