Projects Under Construction

Project Status Contact
Pavement Rehabilitation - Claus Rd. Fact Sheet The contractor has finished majority of the work on the project.  Contractor shall start traffic signal modification soon. Michael Sacuskie
Bus Turnout Improvement Southbound Dale Rd. Contractor construction bids were opened on October 23, 2018.  Awarding of construction contract is scheduled for the November 13, 2018 City Council Meeting.  Construction anticipated to begin in February 2019. Sandeep Sandhu
Westbound D St. to Northbound 9th St. Right Turn Lane Improvements On October 9, 2018, City Council awarded the construction contract.  Construction anticipated to begin in December 2018. Sandeep Sandhu